دراسات الحالة

نتائج على طرق حقيقية

برامج منفَّذة لجهات الشرطة والنقل والبنية التحتية في الإمارات — ما الذي كان مطلوباً، وما الذي ركّبناه، والكميات والتواريخ ومدد الصيانة في كل عقد.

الوثائق التقنية التفصيلية والمقالات متاحة باللغة الإنجليزية.

ملف المشروع 012025
Emirate transport authority, UAESheikh Zayed Road, Abu Dhabi Emirate

Variable speed control on Sheikh Zayed Road

30
Signs delivered
Dec 2025
Completed
Sheikh Zayed Road
Corridor
Central ITS software
Integration

التحدّي

One of the region's busiest corridors needed dynamic speed control that answered to the transport authority's existing central ITS platform rather than operating as a separate island.

ما الذي ركّبناه

Supply, installation, testing and commissioning of 30 variable speed control sign systems along Sheikh Zayed Road, integrated with the authority's central ITS software.

النتيجة

Completed December 2025.

الأنظمةVSCS
ملف المشروع 022025
Emirate police authority, UAEAbu Dhabi Emirate

Seatbelt and mobile-phone detection, 80 systems

80
Systems in programme
Ongoing
Status
Gantry, roadside, bridge
Mountings
Seatbelt, mobile phone
Detects

التحدّي

Behavioural offences inside the vehicle had to be detected across very different road types — high-speed multi-lane highways, urban intersections and bridge crossings — each needing a different mounting position and field of view.

ما الذي ركّبناه

80 systems engineered for flexible deployment: gantry installations for highways and high-speed corridors giving wide-lane, high-accuracy detection; roadside units for urban roads and intersections; and bridge installations for a broader field of view across multiple lanes.

النتيجة

Ongoing programme.

الأنظمةISER SB
ملف المشروع 032024
Emirate police authority, UAEAbu Dhabi Emirate

Emirate-wide speed and red-light enforcement, 883 systems

883
Systems delivered
Nov 2024
Completed
7 years
Maintenance term
Emirate-wide
Coverage

التحدّي

Enforcement coverage was required across an entire emirate's road network — highways, urban corridors and junctions — under one programme rather than as isolated installations, with automatic number-plate recognition and hazard detection built in from the start.

ما الذي ركّبناه

Supply, installation, testing and commissioning of 883 intelligent speed enforcement radars covering both speed and red-light violations, each with an ANPR system and a safety-hazard system, deployed across the emirate.

النتيجة

Completed November 2024 and running under a seven-year maintenance agreement.

الأنظمةISERSolar ISER
ملف المشروع 042023
Emirate police authority, UAEAbu Dhabi Emirate

212 fixed speed enforcement systems with ITS totems

212
Enforcement systems
20
ITS totems
May 2023
Completed
7 years
Maintenance term

التحدّي

Fixed enforcement was needed at scale, paired with variable message signage so the same corridors could both enforce limits and inform drivers.

ما الذي ركّبناه

Supply, installation, handover, maintenance and support of 212 fixed speed enforcement systems with ANPR, together with 20 variable-message ITS totems.

النتيجة

Completed May 2023 and running under a seven-year maintenance agreement.

الأنظمةISERVSCS
ملف المشروع 052023
Emirate police authority, UAEAbu Dhabi Emirate

Replacing every red-light radar in the emirate, 564 systems

564
Systems delivered
Apr 2023
Completed
7 years
Maintenance term
Full fleet replacement
Scope

التحدّي

The emirate's entire installed base of red-light enforcement radars had reached end of life and needed replacing — not supplementing — without leaving junctions unenforced during the transition.

ما الذي ركّبناه

Supply, installation, handover, maintenance and support of 564 fixed red-light enforcement systems with ANPR, replacing all previously installed red-light radars across the emirate.

النتيجة

Completed April 2023 and running under a seven-year maintenance agreement.

الأنظمةIRES
ملف المشروع 062023
Emirate police authority, UAEAbu Dhabi Emirate

270 variable speed control signs

270
Signs delivered
Mar 2023
Completed
Variable, centrally set
Control
Emirate-wide
Coverage

التحدّي

Posted speed limits needed to change with conditions across the network, rather than remaining fixed regardless of weather, congestion or incidents.

ما الذي ركّبناه

Supply, installation, handover, maintenance and support of 270 variable speed control sign systems.

النتيجة

Completed March 2023.

الأنظمةVSCS
ملف المشروع 072023
Emirate police authority, UAEAbu Dhabi Emirate

Pedestrian crossing and wrong-way enforcement, 80 systems

80
Systems delivered
Feb 2023
Completed
Photo and video
Evidence
Pedestrian vs vehicle
Detection

التحدّي

Two distinct risks needed addressing on the same programme: vehicles entering exits and chevron areas the wrong way, and vehicles failing to give way to pedestrians at crossings — the second requiring a system that can tell a pedestrian from a vehicle reliably enough to support a penalty.

ما الذي ركّبناه

Supply, installation, testing and commissioning of 80 combined speed, EXIT-I and PEDI-SAFE systems. EXIT-I records wrong-way violations automatically with photo and video evidence suitable for enforcement and legal proceedings. PEDI-SAFE uses sensors and computer vision to detect pedestrians at crossings and flag vehicles that fail to yield, distinguishing pedestrians from vehicles.

النتيجة

Completed February 2023.

الأنظمةPEDISAFESolar EXIT-IISER
ملف المشروع 082022
Emirate police authority, UAEAbu Dhabi Emirate

Solar emergency warning across 3,000 roadside locations

3,000
Units deployed
Nov 2022
Completed
Solar, off-grid
Power
Remote or automatic
Activation

التحدّي

Drivers needed warning of hazards — low visibility, congestion, collisions and road works — at locations spread across the road network, including sites with no mains electricity available.

ما الذي ركّبناه

Deployment of 3,000 solar-powered emergency warning units with blue, red, amber and white strobe lighting, triggered either remotely from the control room or automatically in response to detected conditions.

النتيجة

Completed November 2022.

الأنظمةSolar EWS
ملف المشروع 092022
Federal infrastructure ministry, UAEFederal road network, UAE

Traffic counting, weigh-in-motion and asset management, federal network

25
Counting systems
5
Weigh-in-motion
26
Communication links
2012–2022
Contract span

التحدّي

A national roads authority needed continuous traffic data — volume, classification and vehicle weight — across its network, together with the communications and cabinet infrastructure to carry that data back to a central asset management system.

ما الذي ركّبناه

Technical assistance and civil engineering for the asset management system: 25 loop-based traffic counting and classification systems, 5 weigh-in-motion systems using loop and piezoelectric sensors, 26 GPRS VPN wireless communication links, and 25 outstation cabinets — supplied, installed, tested and commissioned.

النتيجة

Started January 2012 and completed January 2022, including a nine-year maintenance term — a decade of continuous operation on one contract.

ملف المشروع 102020
Emirate police authority with the national crisis authority, UAEAbu Dhabi Emirate

Public warning system across 2,000 mosques

2,000
Units deployed
2019–2020
Deployment
2019
Operations since
TETRA, CAP-integrated
Network

التحدّي

National crisis management required a way to reach the public directly and immediately across an entire emirate, operating over a secure network rather than public telecommunications, and integrating with the crisis management systems already in service.

ما الذي ركّبناه

Supply, installation, testing, commissioning, operation and maintenance of 2,000 public warning units deployed across mosques in the emirate. The system carries live and pre-recorded announcements over the secure police TETRA network, and works both standalone and through Common Alerting Protocol integration with existing crisis management systems.

النتيجة

2,000 units deployed between 2019 and 2020. Operations and maintenance have run continuously since 2019 — over seven years to date.

ملف المشروع 112018
Emirate police authority, UAEAbu Dhabi Emirate

24 smart enforcement gantries with fog detection

24
Gantries delivered
Oct 2018
Completed
Signage, fog, analytics
Integrated per gantry
Since 2018
In service

التحدّي

High-speed corridors needed more than enforcement at a point: traffic information had to be gathered and relayed back to drivers on the same structure, including in the low-visibility conditions that make Gulf highways dangerous.

ما الذي ركّبناه

Delivery of 24 speed enforcement smart towers and gantries. Each gantry integrates several systems on one structure — variable signage, fog detection and analytics cameras — gathering traffic information and relaying it to motorists.

النتيجة

Completed October 2018.

الأنظمةITS Gantries
الأدلّة

اطلب الأرقام

حين لا يكون العميل قد أتاح دراسة حالة مكتوبة، يظلّ بوسع مهندسينا أن يعرضوا عليك مشاريع مماثلة وأثرها المقاس.

الخطوة التالية

حدّثنا عن موقعك

شاركنا تفاصيل موقع التركيب — طريق سريع أو منطقة مدرسية أو نفق أو معبر مشاة أو موقع ناءٍ — وسيعود إليك مهندسونا بالتهيئة المناسبة وعرض سعر مفصّل.

تواصل معنا مباشرة

+971 2 444 7677info@alliance.ae

الطابق العاشر، برج تشين, مبنى أورينت ترافل, أبوظبي، الإمارات